Important Update

Flagler Memorial Bridge Replacement Project

IMPORTANT UPDATE

Jan. 16, 2013

 

On Monday, Jan. 14, PCL Civil Constructors, Inc., (PCL) the contractor for the Flagler Memorial Bridge Replacement Project, began construction activities on the west side of the Intracoastal Waterway, south of the existing bridge, building the foundations for the new bridge.

 

In order to minimize vibrations adjacent to the existing Flagler Memorial Bridge, PCL will use an impact hammer to drive template piles for the bridge foundations when they encounter hard rock conditions. The impact hammer will be used infrequently and only as needed. However, residents in the area will experience occasional increased noise levels between 8 a.m. and 5 p.m., Monday through Friday, from Wednesday, Jan. 16, through February 2013.